DAACT: completion and compliance of works in France

A DAACT declares completed works compliant with the planning permission. The challenge period starts on town-hall receipt: normally three months, or five for mandatory-inspection cases. After expiry without challenge, a certificate may be requested; the current provision requires delivery within fifteen days. This procedure replaces neither acceptance of the contractor’s works nor checks of private rights.

3 / 5months depending on inspection
  • Official texts cited
  • Sources checked on
  • Drafted with AI assistance, our method

General legal information with official references and dated checks. It is not personalised advice: for a decision that commits you, have your situation checked by a qualified professional.

Julie by AlphaDeep

Illustrative conversation
Example question

Can the period start on the last construction day?

Julie Illustration

No. R462-6 uses town-hall receipt.

Read the references

I can examine your DAACT receipt and help prepare the certificate request for your project.

French law

3 free questions at signup. Avoid names and sensitive information.

Tool

What conditional calendar applies to your DAACT?

The 10 August example shows 10 November under the ordinary period, or 10 January for five months.

julie://tool/echeancierNothing leaves your browser

Fields stay on this page. The Julie button sends your worksheet when you choose to use it.

Fictional example · Your preparation worksheet

The ordinary period for contesting compliance is three months from receipt, subject to checking the file and any notices.

Three-month reference
2026-11-10
  1. Compare completed works with the permit or non-opposition decision.
  2. Collect project-specific certificates and retain town-hall receipt.
  3. Check mandatory-inspection cases with the competent authority.
  4. After expiry without challenge, request the non-contestation certificate; R462-10 provides for delivery within fifteen days.

These reference dates certify neither compliance nor neighbouring owners’ rights. The receipt and municipal notices govern the file.

Answer

Who declares completion and compliance?

The permission holder or architect who directed the works submits the declaration to the town hall. Additional certificates depend on the project. Check the local submission channel and retain receipt evidence, including for online filing.

Code de l'urbanisme, article L462-1Code de l'urbanisme, article R462-1

DAACT: completion and compliance of works in France: Town-hall receipt, Classify inspection, Certificate on request
DAACT: completion and compliance of works in France
Comparison

Which milestones belong in the file?

Receipt controls the calendar
MilestoneEvidence or condition
SubmissionDAACT and required certificates
ReceiptTown-hall acknowledgement
Three or five monthsClassification under R462-7
CertificateRequest following no challenge

Code de l'urbanisme, article R462-6Code de l'urbanisme, article R462-7

Answer

When does the municipal period begin?

It begins when the town hall receives the DAACT, not physical completion or dispatch. The ordinary period is three months. Without a receipt, do not assume the starting date.

Code de l'urbanisme, article R462-6

Answer

When does the five-month period apply?

R462-7 lists mandatory-inspection cases, including certain protected areas, buildings and risk zones. Categories contain exceptions: a risk plan somewhere in a municipality does not place every project within them.

Code de l'urbanisme, article R462-7

The law

What does the governing text say about the daact?

A compter de la date de réception en mairie de la déclaration d'achèvement

Code de l'urbanisme, article R462-6In force since 1 October 2007Read on Légifrance

In plain English: R462-6 starts the period at receipt; R462-7 identifies mandatory inspections. R462-10 governs the certificate request.

Answer

How is the certificate obtained after silence?

After the applicable period without challenge, request the certificate from the competent authority. R462-10, current since 22 February 2026, provides for delivery as of right within fifteen days. Do not reuse the former prefect-substitution mechanism absent from that current text.

Code de l'urbanisme, article R462-10

Answer

Does non-contestation settle every construction dispute?

No. Distinguish planning compliance, contractual acceptance of works, tax declarations and neighbours’ rights. A non-contestation certificate does not establish a right to encroach on private property.

Code de l'urbanisme, article L462-1Code de l'urbanisme, article L462-2

Frequent questions

What else should you know about the daact?

Can the period start on the last construction day?

No. R462-6 uses town-hall receipt.

Code de l'urbanisme, article R462-6

Do five months apply to every DAACT?

No, only statutory mandatory-inspection cases.

Code de l'urbanisme, article R462-7

Does the certificate arrive automatically?

The provision requires a request after the applicable period passes without challenge.

Code de l'urbanisme, article R462-10

Which submission provision applies in 2026?

R462-1 as in force since 29 July 2026, together with municipal submission arrangements.

Code de l'urbanisme, article R462-1

Sources

Which sources explain the daact?

  1. Code de l'urbanisme, article L462-1Légifrance / DILA
  2. Code de l'urbanisme, article L462-2Légifrance / DILA
  3. Code de l'urbanisme, article R462-1Légifrance / DILA
  4. Code de l'urbanisme, article R462-6Légifrance / DILA
  5. Code de l'urbanisme, article R462-7Légifrance / DILA
  6. Code de l'urbanisme, article R462-10Légifrance / DILA
  7. DAACT, fiche vérifiée le 7 juillet 2026; réserve sur ancien renvoi au préfetDILA / Service Public

Texts cited last checked: 19 October 2026