Contract ended before completion: assemble the account

Termination of a public contract requires the reason, incorporated conditions, completed work and supported compensation items. France's administrative-contract documents and Swiss performance rules must be examined independently. Swiss construction withdrawal before completion raises a different question from paying the final account of a completed work. The ledger separates these stages and does not promise recovery of every claimed loss.

Text in force1 January 2023Sources checked1 November 2026

  • Official texts cited
  • Sources checked on
  • Drafted with AI assistance, our method

General legal information with official references and dated checks. It is not personalised advice: for a decision that commits you, have your situation checked by a qualified professional.

Julie by AlphaDeep

Illustrative conversation
Example question

What work had been performed?

Julie Illustration

Prepare findings, inventory, services and payments. Separate completed work from cancelled future work.

Read the references

Your question concerns “Contract ended before completion: assemble the account”. I can help organise the facts and records. Which document have you received or prepared, and is this a French or Swiss matter?

French law

3 free questions at signup. Avoid names and sensitive information.

Answer

Which termination ground was notified?

Separate public interest, fault and other grounds. France's CCAG-Travaux50-51 does not provide identical compensation for every ending.

CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 50CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 51220 : Art. 363220 : Art. 377CCAG-Travaux : arrêté du 30 mars 2021

Answer

What work had been performed?

Prepare findings, inventory, services and payments. Separate completed work from cancelled future work.

Tool

Which records are still missing from your file?

Indicate which records you have. The result identifies gaps and prepares a complete question for Julie, without requiring an account.

julie://tool/echeancierNothing leaves your browser

Answers stay on this page until you explicitly continue to Julie. Avoid names and sensitive information.

Fictional example · Your preparation

Point to complete: Request and termination account. French article 51 provides a distinct account within its contractual scope. Keep notice and debit-credit items rather than one undifferentiated invoice.

Termination act and ground
Record available
Work performed
Record available
Claimed costs
Record available
Request and termination account
Needs checking
Records indicated
3 / 4
  1. Which termination account was served?

This worksheet organises records; it does not establish admissibility, entitlement or a procedural outcome.

Answer

Which claimed costs are supported?

Classify necessary commitments, unrecovered spending and other heads under the applicable clause. A forecast does not prove every lost cost.

Answer

Which termination account was served?

French article 51 provides a distinct account within its contractual scope. Keep notice and debit-credit items rather than one undifferentiated invoice.

Comparison

Which documents answer which questions?

Which documents answer which questions?
Record or informationIssue to check
Termination act and groundSeparate public interest, fault and other grounds. France's CCAG-Travaux50-51 does not provide identical compensation for every ending.
Work performedPrepare findings, inventory, services and payments. Separate completed work from cancelled future work.
Claimed costsClassify necessary commitments, unrecovered spending and other heads under the applicable clause. A forecast does not prove every lost cost.
Request and termination accountFrench article 51 provides a distinct account within its contractual scope. Keep notice and debit-credit items rather than one undifferentiated invoice.

CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 50CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 51220 : Art. 363220 : Art. 377CCAG-Travaux : arrêté du 30 mars 2021

Answer

Which contractual framework is actually incorporated?

Check French CCAG edition and deviations or the actual Swiss public/private framework. Not every procurement is a works contract.

CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 50CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 51220 : Art. 363220 : Art. 377CCAG-Travaux : arrêté du 30 mars 2021

Answer

What does Swiss CO 377 concern?

It addresses customer withdrawal while a work remains unfinished, with work payment and contractor indemnification conditions. It is not a rule for every Swiss service contract or procurement revocation.

CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 50CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 51220 : Art. 363220 : Art. 377CCAG-Travaux : arrêté du 30 mars 2021

The law

Which official provision helps explain this situation?

Le titulaire a droit, en outre, à être indemnisé de la part des frais et investissements, éventuellement engagés pour le marché et strictement nécessaires à son exécution, qui n'aurait pas été prise en compte dans le montant des prestations payées. Il lui incombe d'apporter toutes les justifications nécessaires à la fixation de cette partie de l'indemnité.

CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 50In force since 1 January 2023Read on Légifrance

In plain English: Check French CCAG edition and deviations or the actual Swiss public/private framework. Not every procurement is a works contract.

Answer

How should the supported request be assembled?

Link each head to ground, clause and evidence. Distinguish amounts paid, disputed claims and established expenses.

Answer

What does the termination file deliver?

It organises act, performance, costs and account. It determines no compensation and does not replace an award-stage challenge.

Frequent questions

What other questions arise in this file?

What work had been performed?

Which termination account was served?

Which contractual framework is actually incorporated?

How should the supported request be assembled?

Sources

Which official references should you consult?

  1. CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 50Légifrance
  2. CCAG-Travaux approuvé par arrêté du30mars2021 (contractual incorporation required) art. 51Légifrance
  3. 220 : Art. 363Fedlex
  4. 220 : Art. 377Fedlex
  5. CCAG-Travaux : arrêté du 30 mars 2021Source officielle

Texts cited last checked: 1 November 2026